| Particulars | Details/Status |
|---|---|
| Project Name |
Construction of 4-Lane Greenfield Expressway spur from Delhi-Vadodara Greenfield expressway near Bandikui to Jaipur in Bharatmala Pariyojana Phase-I in the state of Rajasthan on Hybrid Annuity Mode |
| Scheme/Phase | Bharatmala Pariyojana |
| Mode of Execution | Hybrid Annuity Mode (HAM) |
| Concessionaire Name | M/s GR Bandikui Jaipur Expressway Private Limited |
| Date of Letter of Award (LOA) | 30.03.2022 |
| Appointed Date | 11.11.2022 |
| Construction Period (in Days) | 730 Days from the Appointed Date |
| Schedule Completion Date | 09.11.2024 |
| Operation & Maintenance Period | 15 years from COD |
| Independent Engineer | LN Malviya Infra Project Pvt. Ltd. in Association with Pioneer Infra Consultants Pvt. Ltd. |
| Authority Name | National Highways Authority of India, PIU-Dausa, RO-Jaipur |
| No. of Lanes/ Configuration | 4 Lane |
| Bid Project Cost | 1368.00 Cr. |
| Total Length of the Project | 66.916 km |
| No. of Interchanges | 03 nos. |
| No. of ROB | 01 no. |
| No. of Flyovers | 02 nos. |
| No. of Underpasses | VUP-11 nos., SVUP-17 nos. |
| No. of Major Bridges | 02 nos. |
| No. of Minor Bridges | 11 nos. |
| No. of Box Culverts | 136 nos. + 5 nos. additional |
| Toll Plaza | 05 nos. |