| Component | %Weightage as per Schedule-G | Progress achieved (during current month) | Physical Progress achieved (Cumulative, up to current month) | 
|---|---|---|---|
| Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) | 61.95%  | 
0.06%  | 
61.95  %  | 
| Major Bridge Works & ROB/ RUB | 8.23%  | 
0.24  %  | 
8.23  %  | 
| Structures (elevated sections, reinforced earth) | 4.59%  | 
0.04  %  | 
4.59  %  | 
| Electrical and Public Health Utilities | 2.40%  | 
0.65  %  | 
2.40  %  | 
| Other Works | 22.83%  | 
  0.89  %  | 
  22.53  %  | 
Total  | 
  100.00%  | 
  1.88  %  | 
  99.70  %  |