Component | %Weightage as per Schedule-G | Progress achieved (during current month) | Physical Progress achieved (Cumulative, up to current month) |
---|---|---|---|
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) | 61.95% |
0.06% |
61.95 % |
Major Bridge Works & ROB/ RUB | 8.23% |
0.24 % |
8.23 % |
Structures (elevated sections, reinforced earth) | 4.59% |
0.04 % |
4.59 % |
Electrical and Public Health Utilities | 2.40% |
0.65 % |
2.40 % |
Other Works | 22.83% |
0.89 % |
22.53 % |
Total |
100.00% |
1.88 % |
99.70 % |